Available Resources
| Note |
Description |
Summer Peak 2004 |
Winter
Peak 2005 |
Summer Peak 2005 |
Existing Resource Scenario |
Planned Resource Scenario |
Existing Resource Scenario |
Planned Resource Scenario |
Existing Resource Scenario |
Planned Resource Scenario |
| 1 |
Installed Resources(MW) |
30,114 |
30,114 |
30,164 |
30,807 |
30,215 |
30,878 |
| 2 |
Imports(MW) |
0 |
0 |
0 |
0 |
0 |
0 |
| 3 |
Total Resources(MW) |
30,114 |
30,114 |
30,164 |
30,807 |
30,215 |
30,878 |
| 4 |
Total Reductions in Resources(MW) |
3,953 |
3,953 |
1,604 |
1,604 |
1,863 |
1,873 |
| 5 |
Price-responsive Demand(MW) |
352 |
394 |
352 |
449 |
352 |
703 |
| 6 |
Available Resources(MW) |
26,513 |
26,555 |
28,912 |
29,652 |
28,704 |
29,708 |
Notes to Summary of Resources:
1. Installed Resources: This is the total capacity of the existing
installed generation resources in Ontario assumed to be available over
the summer and winter peaks in the 18-month time span. This value includes
all the generators in Ontario, retired generators, embedded generators
not managed by OEFC or generators not directly connected to the IMO-controlled
grid.
2. Imports: Represents the amount of external capacity considered to be reliably committed to Ontario under existing contracts/agreements.
3. Total Resources: This is the sum of lines 1 and 2 above.
4. Total Reductions in Resources: These reductions represent, under each of the two scenarios, the sum of generator deratings, planned generator outages, generation limitations due to transmission interface constraints and allowances for non-utility and hydroelectric generation production below rated capacity.
5. Price-responsive Demand: This is the amount of price-responsive demand assumed under each resource senario.
6. Available Resources: This is the difference between lines 3 and 4 above.
Source: Ontario IMO

|